Zhejiang SeaTrust Power Co., Ltd

Home >> About Us >> News
News From SeaTrust
International tender from Regideso of MT/BT networks of Bujumbura for transmission lines Mar. 30, 2023

Country:The Republic of Burundi

Utility:REGIDESO

Projects Background:


The Regideso launches an international tender notice of a market by restricted consultation of the pre-qualified manufacturers for the supply and delivery of operating equipment, maintenance and extension of MT/BT networks of Bujumbura and centers in the interior of the country.

The characteristics of the material desired by the regideso are defined in the specific technical clauses notebook, as well as in the quantities and prices slip in the appendix.

This market concerns the supply of operating equipment, maintenance and extension of Bujumbura MT/BT networks and interior centers.


Products Lists:

1.Conducteur nu AL-Ac ; 35/6 mm² ;

2.Sectionneur tripolaire 30kv à coupure en charge avec commande manuel et accessoires de fixation sur poteau

3.Parafoudre 30 kV, 10 kA  avec accessoires de fixation sur poteau métallique

4.Traverse d'angle 30 kV, avec accessoires de fixation sur poteaux métalliques

5.Chaînes d'isolateurs d'ancrage complètes à trois éléments avec pinces d'ancrage pour conducteur nu AL-Ac 35/6mm2,  

6.Raccords parallèles pour conducteur nu Al/Ac 35/6mm² , tension 30kV

7.Manchon de jonction à compression pour câble Al-Ac section 35/6mm²

8.Tiges galvanisées et filetées sur toute la longueur avec deux écrous et deux rondelles

9.Poteau métallique tubulaire de 16m, 1000daN, d’angle ou d’arrêt

10.Poteau métallique tubulaire de 16m, 1250daN, support de transformateur

11.Soulier de câble à sertir pour conducteur nu 35/6 mm2

12.Vis à bois galvanisée ou tire-fonds ; 10X120mm ; filetée à 60% pour poteaux bois

13.Transformateur triphasé 50Hz, 160kVA, 30Kv/0,4kv, réglage à vide par commutateur, couplage Dyn11, montage extérieur sur poteau métallique

14.Soulier de câble Al/Cu à sertir pour conducteur 3x35-70mm²

15.Câbles aériens pré assemblés 3X35+1X54,6+1x16mm2

16.Pinces d'ancrage pour neutre porteur pour câble pré assemblé  Al, 35 à 70mm² BT 1000V

17.Pinces de suspension pour câble pré assemblé 35à 70mm² ; BT 1000V

18.Fil de fer rond galvanisé de diamètre 8mm

19.Piquet de mise à la terre, long: 1500mm, en acier cuivré, emboîtable

20.Ruban de terre galvanisé, 30x3mm

21.Pointe pour piquet de terre

22.Raccord de connexion entre ruban de terre et ruban de terre largeur 30mm et épaisseur:3mm

23.Raccord de connexion entre ruban de terre et piquet de terre

24.Raccord de contrôle et de séparation entre fil de fer et ruban de terre


Total Volume:USD 900,000.00


International tender from Regideso of MT/BT networks of Bujumbura for transmission lines

International tender from Regideso of MT/BT networks of Bujumbura for transmission lines

International tender from Regideso of MT/BT networks of Bujumbura for transmission lines


International tender from Regideso of MT/BT networks of Bujumbura for transmission lines
Back to Top
Sierra Leone World Bank.for supply and Installation of 11/0.4kV Distribution Network in Freetown & 11/0.4kV Mar. 23, 2023

Country:Sierra Leone

Utility:EDSA

Total Volume:USD 5,000,000.00

Projects Background:

It was a project invested by World Bank.for supply and Installation of 11/0.4kV Distribution Network in Freetown & 11/0.4kV Distribution Substations (50, 160, 250, 400, 630kVA) & Wood Poles (9m, 10m, 11m, 12m) & Bare and Insulated All Aluminium Conductors (AAC), 50 and 120mmsq & LV Aerial Bundled Conductors (Al) c/w clamps and connectors.

Products Lists

1.11kV, 3Ph Intermediate Pole Top Structure (0 - 3°, Dwg. No. ESURP/AF/11KV/DWG/IMP)

2.11kV, 3Ph Light Angle Pole Top Structure (3° - 20°, Dwg. No. SURP/AF/11KV/DWG/LAP)

3.11kV, 3Ph Medium Angle Pole Top Structure (20°- 60°, Dwg. No. ESURP/AF/11KV/DWG/MAP)

4.11kV, 3Ph Heavy Angle Pole Top Structure (60° - 90°, Dwg. No. ESURP/AF/11KV/DWG/HAP)

5.11kV, 3Ph Terminal Pole Top Structure (Dwg. No. ESURP/AF/11KV/DWG/TP)

6.11kV, 3Ph Sectional Pole Top Structure (Dwg. No. ESURP/AF/11KV/DWG/SP)

7.11kV, 3Ph Tap (Tee - off) Pole Top Structure (Dwg. No. ESURP/AF/11KV/DWG/TOFF)

8.11kV, 3Ph Fused Tee - off Pole Top Structure (Dwg. No. ESURP/AF/11KV/DWG/FTOFF)

9.11kV Load Isolator c/w earth mat

10.Complete 11kV Stay Equipment (ref Dwg. No. ESURP/AF/11kV/DWG/STAY)Set

11.3C x 240mm2, 11kV XLPE/SWA/PVC Cu cable

12.11kV Cable Three Core Termination kits (set of 3-phase, 240mm2)

13.11kV Surge Arrester c/w mounting clamps, earthing etc. (Set of 3-phase)ABC Intermediate Pole Top Structure (0 - 3°, Dwg. No. ESURP/AF/LV/DWG/IMP)

14.ABC Large Angle Pole Top Structure (3°-20°, Dwg No. ESURP/AF/LV/DWG/LAP)

15.ABC Heavy Angle Pole Top Structure (21°-90°, Dwg. No. ESURP/AF/LV/DWG/HAP)

16.ABC Terminal Pole Top Structure (Dwg No. ESURP/AF/LV/DWG/TP)

17.ABC Tee Off Pole Top Structure (Dwg No. ESURP/AF/LV/DWG/TOFF)

18.ABC 3-Way Section Pole Top Structure (Dwg No. ESURP/AF/LV/DWG/3WAY)

19.ABC 4-Way Section Pole Top Structure (Dwg No. ESURP/AF/LV/DWG/4WAY)Tap-off connector (Piecing Screw type)

20.LV Stay Equipment Complete (ESURP/AF/LV/DWG/STAY)

21.50kVA, 11/0.4kV 3 Phase PMT c/w the accessories outlined in note 2 above

22.160kVA, 11/0.4kV 3 Phase PMT c/w the accessories outlined in note 2 above

23.250kVA, 11/0.4kV 3 Phase PMT c/w the accessories outlined in note 2 above

24.400kVA, 11/0.4kV 3 Phase GMT c/w the accessories outlined in note 2 & 630A, 6-way DP

25.630kVA, 11/0.4kV 3 Phase GMT c/w the accessories outlined in note 2 & 1000A, 8-way DP

Sierra Leone World Bank.for supply and Installation of 11/0.4kV Distribution Network in Freetown

Sierra Leone World Bank.for supply and Installation of 11/0.4kV Distribution Network in Freetown

Sierra Leone World Bank.for supply and Installation of 11/0.4kV Distribution Network in Freetown

Sierra Leone World Bank.for supply and Installation of 11/0.4kV Distribution Network in Freetown



Sierra Leone World Bank.for supply and Installation of 11/0.4kV Distribution Network in Freetown & 11/0.4kV
Back to Top
REPUBLIQUE DEMOCRATIQUE DU CONGO La vétusté et la surcharge des équipements et des canalisations MT et BT ne permettent 220/30/6,6 kV Mar. 23, 2023

Country:REPUBLIQUE DEMOCRATIQUE DU CONGO

Utility:Société Nationale d’Electricité

Total Volume:USD 4,000,000.00

Projects Background:

Les réseaux de distribution de la ville de Kinshasa sont sujets à beaucoup de problèmes d’exploitation.

La vétusté et la surcharge des équipements et des canalisations MT et BT ne permettent pas d’alimenter en toute fiabilité tant les charges existantes que les nouvelles.

La SNEL sur fonds propres préfinance un programme de remise en conformité de ces réseaux de distribution afin de fiabiliser la desserte en énergie électrique dans la ville de Kinshasa.

De manière brève, la charge de la ville de Kinshasa est alimentée principalement par deux systèmes de distribution primaire :

Le système 220/30/6,6 kV, composé des postes sources, également nommés postes d’injection 220/30kV de Liminga, de Lingwala et de Maluku ainsi que du poste 132/30 kV de Badiadingi qui fournissent l’énergie à la boucle 30 kV, celle-ci alimentant à son tour le réseau de distribution 6,6 kV.Ce système supporte environ 65% de la charge de la Ville.

Le système 220/20 kV qui alimente le nouveau réseau de distribution 20 kV comporte trois postes d’injection 220/20 kV (Funa,Utexco et Makala) et sera très prochainement renforcé par celui de Kimbanseke en cours de construction dans le cadre du projet EASE .

Il est prévu dans le plan directeur de la SNEL que le réseau 20 kV, actuellement en phase de développement, remplace complètement le réseau 6,6 kV.

Products Lists:

1.Ensemble d'ancrage double câble aérien BT (consoles + pinces)

2.Ensemble d'ancrage simple câble aérien BT (consoles + pinces)

3.Manchon 70 mm² Alu

4.Manchon 35 mm² Alu

5.Manchon 95 Cu/70 mm² Alu

6.Manchon 50 Cu/70 mm² Alu

7.Soulier de câble 95 mm² Cu

8.Soulier de câble 50 mm² Cu

9.Connecteur de dérivation 70/35 mm² Alu

10.Sectionneur MT tête de câble

11.Disjoncteur MT (Vacuum Interrupter)

12.Sectionneur fusible (rupto)

13.Relais de protection (IEC60870-5)

14.Disjoncteur général BT (DGBT)

15.Tableau général BT (TGBT)

16.Jeu de barres BT (5*30mm)

17.Bases fusibles 

18.Réglette ou base fusible

19.Poste de sectionnement BT (PSBT) avec 5 départs

20.Coffret électricien 

21.Coffret mécanicien

22."Appareil de recherche de défaut câble BT

23.Brand:TFN, made in Austria

24.Model:TFN ETDR 10A"

25.Ceinture pour monteur électricien ligne

26.Grimpette pour électricien ligne

27.Echelle  (8m)

28.Multimètre

29.Pince ampéremetrique

30.Megger

31.Mesureur de résistance de terre (TES 1700)

32.Mesureur de champt tournant

REPUBLIQUE DEMOCRATIQUE DU CONGO La vétusté et la surcharge des équipements et des canalisations MT et BT ne permettent  220/30/6,6 kV

REPUBLIQUE DEMOCRATIQUE DU CONGO La vétusté et la surcharge des équipements et des canalisations MT et BT ne permettent  220/30/6,6 kV

REPUBLIQUE DEMOCRATIQUE DU CONGO La vétusté et la surcharge des équipements et des canalisations MT et BT ne permettent  220/30/6,6 kV


REPUBLIQUE DEMOCRATIQUE DU CONGO La vétusté et la surcharge des équipements et des canalisations MT et BT ne permettent  220/30/6,6 kV


REPUBLIQUE DEMOCRATIQUE DU CONGO La vétusté et la surcharge des équipements et des canalisations MT et BT ne permettent  220/30/6,6 kV
Back to Top
Djibouti 63/20kV Substation Transformer Expansion Project - Control and Power Cables Supply Oct. 28, 2022

Project Information:



Project Name: Palmeraie Substation Transformer Expansion Project

Owner: Electricite de Djibouti(EDD)

Awarded Date: 2022.09


What We Supplied:


ZB-KVVP2/22(FRB-CU/PVC/CTS/PVC/STA/PVC)-10×2.5

ZB-KVVP2/22(FRB-CU/PVC/CTS/PVC/STA/PVC)-14×2.5

ZB-KVVP2/22(FRB-CU/PVC/CTS/PVC/STA/PVC)-4×2.5

ZB-KVVP2/22(FRB-CU/PVC/CTS/PVC/STA/PVC)-4×4

ZB-KVVP2/22(FRB-CU/PVC/CTS/PVC/STA/PVC)-8×4

ZB-KVVP2/22(FRB-CU/PVC/CTS/PVC/STA/PVC)-4×6

ZB-KVVP2/22(FRB-CU/PVC/CTS/PVC/STA/PVC)-7×2.5

ZB-VV22(FRB-CU/PVC/PVC/STA/PVC)-4×4

ZB-VV22(FRB-CU/PVC/PVC/STA/PVC)-4×10


Project News:



The project, which is expected o be completed by the end of 2023, includes the construction of a dual fuel diesel power generation station and associated works and accessories, the expansion and development of the transmission network, the measurements, protection, control, and communication systems, and consulting services. The project includes the following main components:


Damerjog Power Generation Station: This includes the construction of Phase I of a diesel powered generation station with installed capacity of 50MW which operates on natural gas and heavy fuel oil, and all civil, mechanical and electrical works for the project’s Phases I and II.


Expansion and Development of the Transmission Network: This includes the construction of two new substations, the expansion and development of two existing substations, the installation of aerial power lines, and the laying of power cables, in addition to civil and electrical works and accessories. This includes the following components:

Nagad Substation: This includes the procurement and installation of equipment and the construction of a new 100 MVA air-insulated substation operating on 230/63/20 kV, as well as civil and electrical works, and systems for measurement, protection, control, and communications, and their accessories.


Damerjog Substation: This includes the procurement and installation of equipment and the construction of a new 100 MVA air-insulated substation operating on 230/63/20 kV, a


Djibouti 63/20kV Substation Transformer Expansion Project - Control and Power Cables Supply
Back to Top
Burundi MT Overhead Power Grid Project - POWER FITTING AND TRANSFORMER Supply Oct. 28, 2022

Project Information:


Owner: REGIE DE PRODUCTION ET DISTRIBUTION D’EAU ET D’ELECTRICITE (REGIDESO)


Project Name: POUR LA FOURNITURE DU MATERIEL D’ENTRETIEN, DE RENFORCEMENT ET D’EXTENSION DES RESEAUX SOUTERRAIN ET AERIEN MOYENNE TENSION (MT) DE BUJUMBURA ET SES ACCESSOIRES.


Delivered Date: 2022.05

Project News:

Le Directeur Général était sur terrain à Kabezi  pour suivre les travaux de  construction de la ligne trente (30)KV Kabezi – poste Kanyosha qui va être bientôt fonctionnelle : elle va transporter dix(10) Mw  produite   par la Centrale hydroélectrique de Ruzibazi et, au finish, la Regideso vise acheminer la totalité de l’énergie produite par les trois(3) groupes de cette Centrale.


Le 1er groupe de 5Mw a commencé à produire fin avril 2022 et le dernier fin Mai. Aujourd’hui, 5MW de cette centrale sont déjà injectés dans le réseau électrique du sud du pays. L’énergie restante va être injectée dans le réseau via Bujumbura.


Enfin, l’ autre  souci du Directeur Général  est la protection de l’environnement pendant  l’abattage des arbres, la fixation des poteaux métalliques le long du corridor de la ligne 30kv. Le respect des normes environnementales reste de mise.


Burundi MT Overhead Power Grid Project - POWER FITTING AND TRANSFORMER Supply

Burundi MT Overhead Power Grid Project - POWER FITTING AND TRANSFORMER Supply

Burundi MT Overhead Power Grid Project - POWER FITTING AND TRANSFORMER Supply

Burundi MT Overhead Power Grid Project - POWER FITTING AND TRANSFORMER Supply


Burundi MT Overhead Power Grid Project - POWER FITTING AND TRANSFORMER Supply
Back to Top
11/33kV distribuition transformer ready to be delivery to State Grid of China Oct. 27, 2022

11/33kV distribution transformer ready to be delivered to State Grid of China


More than 2000pcs transformers are finished producing and are ready to be transported to different cities in China and for installation by State Grid and China South Grid


11/33kV distribuition transformer ready to be delivery to State Grid of China

11/33kV distribuition transformer ready to be delivery to State Grid of China

11/33kV distribuition transformer ready to be delivery to State Grid of China


11/33kV distribuition transformer ready to be delivery to State Grid of China
Back to Top
New Deliery to Ministry of Energy Sierra Leone Oct. 26, 2022

New Deliery to Ministry of Energy Sierra Leone


The projects was participated from Dec.2021 with our partner in Sierre Leone but for Ministry of Energy. After one year communication, we ship the finsihed products to Free Town Sierra Leone around the end of Sep.


The products include:

11kV 2000x100x75x5mm galvanised steel crossarm

5/8x9 inches bolt and nut complete with washers

5/8x4 inches bolt and nut complete with washers

5/8x15 inches bolt and nut complete with washers

1/2x6 inches bolt and nut complete with washers

1/2x15 inches bolt and nut complete with washers

Steel galvanished 700x100x100x5mm Angle Iron

0.6/11kV ABC overhead line Tension Clamp

Pole clamp and support bracket for Tension clamp of MV ABC

715x50x4mm Steel Galvanished Tie Strap

2500x100x50x4mm galvanished steel perforated C Channel

0.415/1kV ABC overhead line Tension Clamp

Pole clamp and support bracket for Tension clamp of 1kV ABC(9m)

Pole clamp and support bracket for Tension clamp of 1kV ABC(12m)

110x118x4mm steel D-iron complete (with insulator)

Anchoring clamp for MV ABC Cable

Pole clamp and support bracket for Anchoring clamp of MV ABC

Suspension clamp for MV ABC Cable

Pole clamp and support bracket for Suspension clamp of MV ABC

New Deliery to Ministry of Energy Sierra Leone

New Deliery to Ministry of Energy Sierra Leone

New Deliery to Ministry of Energy Sierra Leone


New Deliery to Ministry of Energy Sierra Leone
Back to Top
Angola 220/150/60kV Substation Project -POWER FITTING Supply Oct. 25, 2022

Angola 220/150/60kV Substation Project -POWER FITTING Supply

Project Information:



Project Name: Subestação Eléctrica de Castelo Branco 220/150/60kV

Owner: MINISTRY OF ENERGY AND WATER (MINEA)

EPC Contractor: Electro Force

Delivery Date: 2022.09


What We Supplied:


CABLE LXHIOV 1X120/16 18/30(36)kV

CABLE ASTER LA56

CABLE PARTRIDGE LA160

CABO COBRE GENLIS HO7V-R 450/750V 1X35 AM-VD

CABO XV 0,6/1KV 1X70

CABO XV 0,6/1KV 1X150

CABO XV 0,6/1KV 1X240


Project News:



Subestação eléctrica constituída por 2 Painéis blindados isolados a gás (GIS) de 400kV

Trabalhos Executados:

Montagem de toda Rede de Terras aérea;

Montagem de todas as estruturas metálica;

Montagem de todos os equipamentos AT, MT e BT;

Passagem e ligação de todos os cabos AT, MT e BT (potencia e comando);

Montagem e ligação da iluminação interior e exterior da Subestação;

Montagem da Instalação eléctrica geral nas Salas técnicas.


Angola 220/150/60kV Substation Project -POWER FITTING Supply
Back to Top
Myanmar Transmission Line Conductor Replacing Project - Conductors Supply Oct. 09, 2022

Myanmar Transmission Line Conductor Replacing Project - Conductors Supply

Project Information:


Project Name: Design, Supply, Construction and Commissioning of Conductor Replacing(Turnkey) (132kV Mann-Magway Transmission Line, 61.3km)

Owner: Department of Power Transmission and System Control

Awarded Date: 2022.09


What We Supplied:


Formed Annealed Aluminium Conductors Carbon Fiber Composite Core Supported ASTM-JLRX1/F1B-250/28


Applicable Standards:


ASTM B 609

ASTM B 857

ASTM B 987


Project News:


The DPTSC (Department of Power Transmission and System Control) has allocated funds to finance the cost of turnkey system for Material Supply, Conductor Replacing and Commissioning Work of 132kV Mann-Magway Transmission Line of Myanmar Power System Grid. 

Material Supply & Conductor Replacing Work (Transmission Line): 132kV, Mann-Magway Transmission Line LOT(1), 61.3 km

Existing Conductor: ACSR 397.5MCM (IBIS)

New Replacing Conductor: ACCC 491MCM (GDANSK)






Myanmar Transmission Line Conductor Replacing Project - Conductors Supply
Back to Top
Cable inspection on July 29, 2020 Aug. 03, 2020

INSULATED STRAIN COPPER EARTHING WIRE, CU/XLPE/PVC, LV 600/1000V & MV 12KV CABLES FOR PROCUREMENT OF MV & LV MATERIALS AND ACCESSORIES FOR POWER DISTRIBUTION NE

INSULATED STRAIN COPPER EARTHING WIRE, CU/XLPE/PVC, LV 600/1000V

INSULATED STRAIN COPPER EARTHING WIRE, CU/XLPE/PVC, LV 600/1000V


INSULATED STRAIN COPPER EARTHING WIRE, CU/XLPE/PVC, LV 600/1000V


Cable inspection on July 29, 2020
Back to Top
Nice work of 40MVA transformer Sep. 05, 2019

Nice work of 40MVA transformer

Nice work of 40MVA transformer

Nice work of 40MVA transformer

Nice work of 40MVA transformer

Nice work of 40MVA transformer


Nice work of 40MVA transformer
Back to Top
3200pcs of Disconnection Switches delivery to Indonesia Sep. 05, 2019

3200pcs of Disconnection Switches delivery to Indonesia

3200pcs of Disconnection Switches delivery to Indonesia

3200pcs of Disconnection Switches delivery to Indonesia

3200pcs of Disconnection Switches delivery to Indonesia


3200pcs of Disconnection Switches delivery to Indonesia
Back to Top
FAT from Uganda REA for power cable accessories and so on Sep. 05, 2019

FAT from Uganda REA for power cable accessories and so on

FAT from Uganda REA for power cable accessories and so on

FAT from Uganda REA for power cable accessories and so on

FAT from Uganda REA for power cable accessories and so on

FAT from Uganda REA for power cable accessories and so on

FAT from Uganda REA for power cable accessories and so on


FAT from Uganda REA for power cable accessories and so on
Back to Top
First delivery to East Africa after CNY holiday Feb. 22, 2019

First delivery to East Africa after CNY holiday with CKD solution. Good beginning of 2019


First delivery to East Africa after CNY holiday

First delivery to East Africa after CNY holiday


First delivery to East Africa after CNY holiday
Back to Top
Happy Chinese New Year 2019!! Feb. 11, 2019

Happy Chinese New Year 2019!!

We are on the way!!

Happy Chinese New Year 2019!!
Back to Top
Cargo arrive MOEE warehouse for C1-G6 projects Jan. 29, 2019

Cargo arrive MOEE warehouse for C1-G6 projects, our engineers go and help MOEE to check the items and finish the final inpection. We will keep offering support to MOEE in the future.


Cargo arrive MOEE warehouse for C1-G6 projects

Cargo arrive MOEE warehouse for C1-G6 projects

Cargo arrive MOEE warehouse for C1-G6 projects


Cargo arrive MOEE warehouse for C1-G6 projects
Back to Top
MOEE Factory inspection for C1-G6 contract Oct. 12, 2018

Our Guests from MOEE to inpsect the contact of C1-G6, the inspection products include Power Cable, Switch Gear, Power fitting, Surge Arrest and so on. 


The Whole team stay in China around one week include a consulator from Korea


MOEE Factory inspection for C1-G6 contract
Back to Top
Fast power solution Aug. 24, 2017

Fast power solution

Good technical support

Stable order supply

Responsible merchant contract sprit


Fast power solution
Back to Top
FACTORY Aug. 24, 2017

Zhejiang SeaTrust Power Co., Ltd has strict quality control system based on ISO9001 standard with high efficient producing machine such as: FORGING COMPRESSION WORKSHIP, HYDRAULIC COMPRESSION MACHINE, HYDRAULIC COMPRESSION MACHINE, DIE PROCESSING CENTER and so on.


The new producing base is more than 30,000 m2, we have more than 500 workers include 22 engineers for new items design and development. SeaTrust also have very professional overseas team to give good support in the site view and customized products supply.


FACTORY
Back to Top

Copyright © 2017 Zhejiang SeaTrust Power Co., Ltd. All rights reserved.   

Top